Das Island Residential Development (DIRD)
Das Island, Abu Dhabi.
– 33/11 KV Power Substation (Design and Build Based on Feed Design).
– Provide fully redundant control SCMS Scheme to allow local operations and remote monitoring / operation from Company control room in DAS Island.
-Provide Fully redundant DMS System.
– Terminal Pointshall be the existing 33KV GIS (80-SWB-J2) switchgear in DAS Island.
– Control Cabling from the Inter tripping relays and interlocking between the tie in switchgear and the new 33KV Switchgear art the Proposed Switchgear at the Proposed 33Kv Primary Substation.